2024 Call Room Renovation Schedule
Select House Officer Call Rooms are to be refurbished. Construction begins April 12.
The Hospital makes improvements to call rooms on a rotating basis. The slate of call rooms has been determined for this year. The renovations will include updates or maintenance to flooring and furniture, as well as a fresh coat of paint. During construction, rooms will be entirely unavailable to house officers.
Construction on each room begins 7am on a Monday, and will be finished by the end of business that Friday. Displaced house officers will be assigned another call room during remodels. Look for an email from your Program Administrator with the code to your alternate room. Program Administrators will also communicate any changes to the schedule.
All personal items should be removed from each room the Sunday evening before the construction is scheduled to start. Security will remove any items left behind, including anything left in the lockers. All locks left on lockers will be cut.
Schedule
Room | Start Date | End Date | Temporary Call Room | Status |
---|---|---|---|---|
C&W 3-330 (Room 17) | Mon 4/8 | Fri 4/12 | C&W 3-316 (Room 10) C&W 3-355 (Room 29) | Complete |
UH 4815 | Mon 4/8 | Fri 4/12 | UH 5218 | Complete |
C&W 3-324 (Room 14) | Mon 4/15 | Fri 4/19 | C&W 3-316 (Room 10) | Complete |
UH 4825 | Mon 4/15 | Fri 4/19 | UH 5218 | Complete |
C&W 3-326 (Room 15) | Mon 4/22 | Fri 4/26 | C&W 3-316 (Room 10) | Complete |
UH 5708 | Mon 4/22 | Fri 4/26 | UH 5218 | Complete |
C&W 3-328 (Room 16) | Mon 4/29 | Fri 5/3 | C&W 3-316 (Room 10) | Complete |
UH 6603 | Mon 4/29 | Fri 5/3 | UH 5218 | Complete |
C&W 3-320 (Room 12) | Mon 5/6 | Fri 5/10 | C&W 3-316 (Room 10) | In Progress |
C&W 3-322 (Room 13) | Mon 5/6 | Fri 5/10 | C&W 3-355 (Room 29) | In Progress |
C&W 3-312 (Room 8) | Mon 5/13 | Fri 5/17 | C&W 3-355 (Room 29) | Not Started |
C&W 3-316 (Room 10) | Mon 5/13 | Fri 5/17 | None | Not Started |